Post by TCU 2U2 on Mar 28, 2013 10:35:03 GMT -5
tsohd put it up ...
Good afternoon:
The FAA is still in the process of making a decision on the CWO competitive procurement as the contracts have not yet been signed and therefore are not yet awarded. As a result, the FAA is postponing the paper debriefs NLT March 31, 2013.
Thank you.
Kathie Petito-Peverall, Contracting Officer, AAQ-230 Facilities & Flight Services Contracts Branch Terminal & EnRoute Contracts Division Office : (202)385-8591 Fax : (202) 493-4612
1 - wonder if the paper debrief was done?
2 - does indicate that the awards have not been awarded.
It this is still the case, what or who could be protesting?
|
|
|
Post by tornado on Mar 28, 2013 11:09:41 GMT -5
If that is true, then the delay in awarding contracts is not due to the sequester. Far be it from the government to say one thing, and do another, however. Also, since Mar. 31st is Sunday, the debriefs should be made known today or tomorrow.
|
|